A letter to notify your builder of defects, with the schedule that goes with it.
A one-page letter in plain words, a numbered schedule of defects with nine columns, and four worked items from an apartment building’s common property. For owners, owners corporations and the strata managers who write for them. Download it in Word, or the schedule on its own in Excel. No form, no email.
Dear [name],
I am writing to notify you in writing of defects in the building work at [property address], carried out under our contract dated [contract date]. Practical completion was on [date].
The defects are listed in the attached schedule. Each one is numbered, with its location, a description, the date it was first noticed and the photographs that show it. Items marked as reported before were first raised with you on the date shown.
Please arrange to inspect the defects and tell me in writing, by [reply date, 14 days from today], when you will rectify them. Access can be arranged through [name] on [phone].
Please quote the item numbers in your reply, so each item keeps one record from this notice to its sign-off.
I have kept a copy of this letter and the photographs.
Yours sincerely,
| No. | Location | Defect | First noticed | Photos | Reported before | Builder’s response | Rectified on | Checked by |
|---|---|---|---|---|---|---|---|---|
| DN-01 | Basement B1, car spaces 14 to 18, east wall | Water seeping through the wall below the ground-floor planter; white efflorescence on 3 m of wall and a puddle after rain | 2026-07-21 | DN-01-a.jpg to DN-01-c.jpg | Email to site manager, 4 Aug 2026 | Replied 11 Aug: will inspect, no date given | — | — |
| DN-02 | Ground floor, main entry door | Door closer slams and the door does not latch on its own, so the building is left unsecured | 2026-09-02 | DN-02-a.mp4 | No | — | — | — |
| DN-03 | Level 3 corridor, outside lots 305 and 306 | Carpet join lifting along 1.2 m, leaving a trip edge | 2026-09-15 | DN-03-a.jpg | No | — | — | — |
| DN-04 | Roof, north drain | Water ponding about 1.5 m across around the drain two days after rain; membrane lap lifting at the upstand | 2026-10-03 | DN-04-a.jpg, DN-04-b.jpg | Phone call to site manager, 6 Oct 2026 | — | — | — |
What each column is for
The letter is short on purpose: it says who you are, what the work is, that the defects are attached, and when you need an answer. The schedule carries the detail, and its columns are what make the notice hard to argue with later.
- 01No.
- A number for each item, assigned once and quoted in every letter and reply after this one. DN-01 stays DN-01 when the builder answers, when it is fixed and when it is signed off.
- 02Location
- Where it is, precisely enough for someone who has never been in the building: level, area, and the nearest thing with a number on it. “Basement B1, car spaces 14 to 18, east wall” is a location; “the car park” is not.
- 03Defect
- What is wrong and how much of it, in words a stranger can check against the photo. Describe what you can see, not what you think caused it.
- 04First noticed
- The date you first saw it. Not the date of the letter. If the period is close to ending, this is the date that matters.
- 05Photos
- The filenames of the photos or videos sent with the letter, named so they sort by item. A photo with a date on it is worth more than a paragraph.
- 06Reported before
- If the item was raised before, how and when: an email, a call, a site meeting. Write “No” if this letter is the first notice.
- 07Builder’s response
- For your own copy: what the builder said about this item, and when. The letter goes out with this column empty.
- 08Rectified on
- For your own copy: the date the builder says the work was done.
- 09Checked by
- For your own copy: who on your side looked at the fix against the original photo, and when. An item is finished when this is filled in, not before.
Four items from one building’s common property
DN-01, the basement wall. Reported once by email in August and answered with a promise to inspect and no date. It goes on the schedule anyway, with Reported before filled in, so the letter shows the item is not new and the builder has already had six weeks. The description says what can be seen, the water and the efflorescence, and leaves the cause to the builder.
DN-02, the entry door. First notice, so Reported before says No. A video shows a closer that slams and a door that does not latch better than any description, and the description says why it matters: the building is left open.
DN-03, the carpet join. Small, but a trip edge in a common corridor is the owners corporation’s problem until it is fixed. The location names the two lot numbers either side, so the builder’s carpet layer finds it without a phone call.
DN-04, the roof drain. Raised by phone in October, which is exactly the notice that gets lost, so it is in writing now with the date of the call. Two photos, two days after rain, because ponding that has dried by the time anyone looks is ponding nobody believes.
Where defect notices go wrong
A letter and a spreadsheet work for one notice and a handful of items. They go wrong in three predictable ways, usually across the months of the defects liability period.
Questions about notifying a builder of defects
Number every item once, and keep one schedule.
Whoever is writing these letters, the record that matters is one numbered schedule with the date each item was first noticed and notified, the photo on the row, the builder’s answer beside it and a check on your side before it closes. If a letter and a spreadsheet are doing that, keep them.
For builders and strata managers running a whole building’s defects liability period, DLP defect tracking shows how IssuesId carries the register over from practical completion, lets owners report from a QR card, sends the trade a link to fix it with a photo, and keeps the check against the original photo on the record. The defects liability period by state sets out the clocks, the DLP inspection checklist is the walk that finds the items, and owners corporations whose builder has stopped replying can read what to do next. The words are in the glossary under defects liability period and rectification.