Defect notification letter

A letter to notify your builder of defects, with the schedule that goes with it.

A one-page letter in plain words, a numbered schedule of defects with nine columns, and four worked items from an apartment building’s common property. For owners, owners corporations and the strata managers who write for them. Download it in Word, or the schedule on its own in Excel. No form, no email.

1 LETTER · 9-COLUMN SCHEDULE · 4 EXAMPLE ITEMS · NO GATE
[Your name, or the owners corporation’s name]
[Address for replies] · [Phone] · [Email]
[Date]
[Builder’s name]
[Builder’s address]
Builder registration or licence number: [number]
Re: Notice of defects at [property address]

Dear [name],

I am writing to notify you in writing of defects in the building work at [property address], carried out under our contract dated [contract date]. Practical completion was on [date].

The defects are listed in the attached schedule. Each one is numbered, with its location, a description, the date it was first noticed and the photographs that show it. Items marked as reported before were first raised with you on the date shown.

Please arrange to inspect the defects and tell me in writing, by [reply date, 14 days from today], when you will rectify them. Access can be arranged through [name] on [phone].

Please quote the item numbers in your reply, so each item keeps one record from this notice to its sign-off.

I have kept a copy of this letter and the photographs.

Yours sincerely,

[Name]
[Role, for example Secretary, Owners Corporation No. 1 PS612345]
Attached: schedule of defects ([number] items) and photographs.
Schedule of defects, as attached
No.LocationDefectFirst noticedPhotosReported beforeBuilder’s responseRectified onChecked by
DN-01Basement B1, car spaces 14 to 18, east wallWater seeping through the wall below the ground-floor planter; white efflorescence on 3 m of wall and a puddle after rain2026-07-21DN-01-a.jpg to DN-01-c.jpgEmail to site manager, 4 Aug 2026Replied 11 Aug: will inspect, no date given——
DN-02Ground floor, main entry doorDoor closer slams and the door does not latch on its own, so the building is left unsecured2026-09-02DN-02-a.mp4No———
DN-03Level 3 corridor, outside lots 305 and 306Carpet join lifting along 1.2 m, leaving a trip edge2026-09-15DN-03-a.jpgNo———
DN-04Roof, north drainWater ponding about 1.5 m across around the drain two days after rain; membrane lap lifting at the upstand2026-10-03DN-04-a.jpg, DN-04-b.jpgPhone call to site manager, 6 Oct 2026———
Fill in the words in brackets. The schedule’s first six columns go to the builder; the last three are for your own copy, to track each item to its sign-off. The four items are the worked examples further down.
The columns

What each column is for

The letter is short on purpose: it says who you are, what the work is, that the defects are attached, and when you need an answer. The schedule carries the detail, and its columns are what make the notice hard to argue with later.

01No.
A number for each item, assigned once and quoted in every letter and reply after this one. DN-01 stays DN-01 when the builder answers, when it is fixed and when it is signed off.
02Location
Where it is, precisely enough for someone who has never been in the building: level, area, and the nearest thing with a number on it. “Basement B1, car spaces 14 to 18, east wall” is a location; “the car park” is not.
03Defect
What is wrong and how much of it, in words a stranger can check against the photo. Describe what you can see, not what you think caused it.
04First noticed
The date you first saw it. Not the date of the letter. If the period is close to ending, this is the date that matters.
05Photos
The filenames of the photos or videos sent with the letter, named so they sort by item. A photo with a date on it is worth more than a paragraph.
06Reported before
If the item was raised before, how and when: an email, a call, a site meeting. Write “No” if this letter is the first notice.
07Builder’s response
For your own copy: what the builder said about this item, and when. The letter goes out with this column empty.
08Rectified on
For your own copy: the date the builder says the work was done.
09Checked by
For your own copy: who on your side looked at the fix against the original photo, and when. An item is finished when this is filled in, not before.
Filling it in

Four items from one building’s common property

DN-01, the basement wall. Reported once by email in August and answered with a promise to inspect and no date. It goes on the schedule anyway, with Reported before filled in, so the letter shows the item is not new and the builder has already had six weeks. The description says what can be seen, the water and the efflorescence, and leaves the cause to the builder.

DN-02, the entry door. First notice, so Reported before says No. A video shows a closer that slams and a door that does not latch better than any description, and the description says why it matters: the building is left open.

DN-03, the carpet join. Small, but a trip edge in a common corridor is the owners corporation’s problem until it is fixed. The location names the two lot numbers either side, so the builder’s carpet layer finds it without a phone call.

DN-04, the roof drain. Raised by phone in October, which is exactly the notice that gets lost, so it is in writing now with the date of the call. Two photos, two days after rain, because ponding that has dried by the time anyone looks is ponding nobody believes.

The limit

Where defect notices go wrong

A letter and a spreadsheet work for one notice and a handful of items. They go wrong in three predictable ways, usually across the months of the defects liability period.

Month eleven
The first notice was a phone call
The roof drain was mentioned to the site manager in October and nobody wrote it down. At the end of the period the builder says it was never reported, and the only evidence is a call log that shows a call, not what was said. Items notified inside the period stay the builder’s to fix; an item nobody can prove was notified is an argument.
The months after
One letter, then forty texts
The letter listed four items. Since then the committee has sent nine more by email and text, two of them twice under different descriptions, and the builder’s replies refer to “the leak” and “the door”. Without one numbered schedule, nobody can say how many items are open.
Sign-off
Fixed, says the builder
The builder’s email says DN-01 to DN-04 are rectified. Nobody went down to B1 after rain to look at the wall, and the efflorescence is back by winter. Rectified on is the builder’s claim; Checked by is yours, and an item is not finished until both are filled in.
Asked alongside the download

Questions about notifying a builder of defects

How do I notify a builder of defects?
In writing, with every defect listed: where it is, what is wrong, when you first noticed it and a photo. Send it to the address the contract gives for notices, by a method that leaves a record such as email or registered post, ask for a reply by a set date, and keep a copy. A phone call or a conversation on site is a start, but follow it with a letter.
What should a defect notification letter include?
Your name and address for replies, the builder’s name and registration or licence number, the property address, the contract date and the practical completion date, a statement that defects are attached, a date for the builder to reply by, and how to arrange access. The detail goes in a numbered schedule: location, description, date first noticed, photos and whether the item was reported before.
Is there a deadline for telling the builder about defects?
There are two clocks. The defects liability period in the contract, commonly twelve months on AS 4000 contracts or thirteen weeks on HIA domestic contracts, and the statutory warranty period in your state, which is longer. Notify each defect as soon as you find it, and before the defects liability period ends for anything found in it. Our defects liability period page sets out the figures by state.
What if the builder does not reply?
Follow up in writing with a new reply date and keep both letters and the proof they were sent. If there is still no answer, the next step is your state’s building regulator or domestic building dispute service. Owners corporations have extra steps of their own, covered in our answer on what to do when the builder will not fix defects.
Is the letter template free, and in what format?
Yes. A Word document with the letter and the schedule of defects on the second page, and the schedule on its own in Excel with extra columns for the builder’s response and your sign-off. Four worked items from an apartment building’s common property are included. No form, no email.
What to do about it

Number every item once, and keep one schedule.

Whoever is writing these letters, the record that matters is one numbered schedule with the date each item was first noticed and notified, the photo on the row, the builder’s answer beside it and a check on your side before it closes. If a letter and a spreadsheet are doing that, keep them.

For builders and strata managers running a whole building’s defects liability period, DLP defect tracking shows how IssuesId carries the register over from practical completion, lets owners report from a QR card, sends the trade a link to fix it with a photo, and keeps the check against the original photo on the record. The defects liability period by state sets out the clocks, the DLP inspection checklist is the walk that finds the items, and owners corporations whose builder has stopped replying can read what to do next. The words are in the glossary under defects liability period and rectification.