A pre-completion inspection checklist, with the hold points marked.
Fifty-five checks across nine areas of a residential unit, four of them hold points, each phrased so Yes means it passes. Download it, copy it into a sheet, or read why the checks are the checks and where a paper checklist breaks. No form, no email.
- Front door closes and latches without lifting or forcing
- Lockset and all keys operate; keys tagged to the unit
- Door stop fitted; door does not strike a wall or fitting
- Intercom or access control rings and releases
- Entry floor finish level, no lippage or cracked tiles
- Walls free of marks, patching shadows and nail pops
- Cornice continuous; no gaps or cracked joins
- Skirting fixed, gaps caulked and painted
- Windows open, close and lock; weep holes clear
- Window reveals and sills sealed; no daylight at frames
- Floor finish free of scratches, gaps and squeaks
- Every GPO and switch tested live
- TV and data points terminated and live
- Air conditioning runs on heat and cool; condensate drains
- Blinds or curtains fitted and operate
- Benchtop joins sealed and flush
- Cupboard doors aligned; handles fixed
- Drawers run to full extension and self-close
- Splashback silicone continuous at bench and wall
- Sink drains freely; no leak under bench after running
- Mixer operates; no drip at rest
- Dishwasher connected, cycles, no leak
- Rangehood runs and vents; filter fitted
- Cooktop and oven operate on every element
- GPOs above bench live and clear of the splashback edge
- Waterproofing certificate sighted for this wet areaHOLD
- Tiles level, no cracks, no drummy tiles
- Grout complete and consistent; no missing runs
- Silicone continuous at wall-to-floor and wall-to-wall junctions
- Floor falls to waste; no ponding after water testHOLD
- Shower screen sealed; no leak outside the screen after test
- Vanity drains; no leak under after running
- Toilet flushes fully and stops; no running cistern
- Exhaust fan runs and vents
- Mirror, rails and accessories fixed and level
- Door closes and latches; no rub on carpet
- Robe doors aligned and run freely
- Robe shelving and rail fixed and level
- Carpet seams tight; edges tucked
- Windows open, close and lock
- Taps operate; no drip at rest
- Tub drains freely; no leak under
- Washing machine and dryer points live
- Floor waste present and clear
- External door seals; no daylight at threshold
- Falls to drain; no ponding after water test
- Balustrade fixed and secure under loadHOLD
- Door threshold sealed; no water entry after test
- Tiles or decking sound; no drummy or loose units
- Smoke alarm tested and interconnectedHOLD
- Switchboard labelled; RCDs test and reset
- Hot water unit runs; temperature at the furthest outlet
- Water meter and isolation valve located and labelled
- Gas isolation located and labelled
- NBN or fibre termination fitted and live
- Unit number fitted at door and letterbox
- Letterbox key operates
- Garage door remote and manual release operate
- Storage cage door locks; number fitted
What each column is for
A pre-completion checklist does two jobs: it finds what is not finished, and it proves what was checked. The first five columns do the finding; the last five do the proving, and they are the ones left blank on most sheets.
- 01Ref
- An area letter and an item number, the same on every unit, so a defect can quote “D3” and everyone knows it is the grout in the shower niche without opening the sheet.
- 02Area
- The room or system the check belongs to. The walk goes area by area, so the sheet does too.
- 03Check
- One observable thing, phrased so that Yes means it passes. “Silicone continuous at wall-to-floor junction” can be answered standing in the room; “bathroom finished to a good standard” cannot.
- 04Result
- Pass, Fail or N/A. A Fail is a defect, and the defect gets raised on the register with a photo at the moment of the Fail, not typed up that evening from the sheet.
- 05Hold point
- Yes for the four checks a unit cannot be signed off without: the waterproofing certificate, falls to waste, the balustrade and the smoke alarm. A hold point is not a severity; it is a rule that the walk does not finish with it open.
- 06Defect no.
- The number of the defect raised for a Fail, on your register. This column is what joins the inspection to the list the trades work from; without it the two drift apart by Thursday.
- 07Photo
- The filename of the photo taken at the check. Take one for every Fail and every hold point, even the passes, because the hold point is the one someone will ask about later.
- 08Checked by
- Who answered it. A check answered by the site manager and one answered by the apprentice are both valid; the reader needs to know which.
- 09Checked on
- The date answered. Not the date the sheet was tidied up.
- 10Notes
- Anything else: a measurement, what was tested and for how long, what the trade said. Never a substitute for the Result column.
Three rows from one ensuite
D3, grout missing. Fail. A photo taken standing in the shower, a defect raised on the register as ABC-214 at the moment of the Fail, the number written back into the Defect no. column. The note says where and how much: left return of the niche, 300 mm run. The tiler can find it from the note alone.
D5, falls to waste. Pass, and a hold point, so it gets a photo anyway and the note records the test: ten minutes of water, drained in forty seconds. In month seven, when the owner says the floor ponded from day one, this row is the answer.
H1, smoke alarm. Pass, hold point, photo, note that both alarms sounded and the interconnect was confirmed. Nobody signs this unit off without it, and the sheet shows who confirmed it and when.
Where a paper checklist breaks
A checklist on paper, or in an app that only produces a PDF, works for one inspector on a handful of units. It fails in three predictable ways, none of them about how carefully it was filled in.
Questions about the checklist
Make the Fail raise the defect, and make the hold point hold.
The two breaks that matter are the gap between the Fail and the register, and a hold point that nothing enforces. Whatever runs your checklist should close both: a Fail raises the defect, with the photo, linked to the check, so there is nothing to type up; and a hold point left open shows on every list until it is released.
That is how IssuesId runs it. Build this list once as a checklist template, mark D1, D5, G2 and H1 as hold points, and run it on every unit. A No raises the defect linked to the question and flips back to Yes when the defect closes; the organisation-wide checklists list flags every open hold point; and the handover walk prints from the Door Sheet, one page per room. The wider pre-handover list is at snagging software, and the terms are in the glossary under practical completion and hold point. If the sheet is working, keep it; the checks above are the part that matters.