A construction punch list template, with the columns explained.
Seventeen columns, four worked punch items from one floor of a medical office fit-out, and one line on why each column is there. Who punched it, whether it is incomplete, defective or damaged, and whether it has to close before substantial or final completion, all on the sheet. Download it, copy it into a sheet, or read where a punch list breaks. No form, no email.
| Item # | Floor | Room | Description | Type | Trade | Subcontractor | Photo | Punched by | Date punched | Close by | Due | Status | Sub completed on | Back-punched by | Closed on | Notes |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| P-0207 | 2 | Exam 214 | Paint touch-up, wall behind door, scuffs from hardware install, 3 locations | Damaged | Painting | Brightline Painting | IMG_3311.jpg | GC pre-punch | 2026-10-06 | Substantial completion | 2026-10-10 | Closed | 2026-10-09 | K. Brooks (super) | 2026-10-09 | Hardware sub accepted the damage; painter back-charged per agreement. |
| P-0208 | 2 | Corridor 2A | Exit sign over door 2A-3 not illuminated on battery test | Defective | Electrical | Lakeside Electric | IMG_3314.jpg | GC pre-punch | 2026-10-06 | Life safety | 2026-10-06 | Closed | 2026-10-06 | D. Ortiz (QA) | 2026-10-06 | Battery pack replaced same day; 90-minute test passed. |
| P-0219 | 2 | Restroom 2B | Grab bar not installed at water closet, side wall; blocking in place | Incomplete | Specialties | Summit Specialties | IMG_3342.jpg | Architect | 2026-10-08 | Substantial completion | 2026-10-13 | Sub complete | 2026-10-13 | — | — | Check mounting height against the accessibility detail at back-punch. |
| P-0231 | 1 | Lobby 101 | Storefront door threshold, daylight visible at latch side, bottom corner | Defective | Glazing | Clearview Glass | IMG_3360.jpg | Owner’s rep | 2026-10-09 | Final completion | 2026-10-23 | Rejected | 2026-10-20 | K. Brooks (super) | — | Back-punch 21 Oct: sweep adjusted, gap still at bottom corner. Re-issued. |
What each column is for
A punch list does two jobs: it gets each item to the sub who owns it, and it proves each item was back-punched before it closed. The first twelve columns do the first job; the last five do the second, and they are the ones a walk sheet usually leaves out.
- 01Item #
- A permanent number, assigned once and never reused. It does not encode the floor, the room or the sub, because all three can change and the number must not.
- 02Floor
- Floor or level, as its own column so a filter for the second floor returns the second floor.
- 03Room
- The room number or name from the drawings. “Exam 214” is a room; “the one by the nurse station” is not.
- 04Description
- What is wrong or unfinished, where on the thing, and how much. “Paint touch-up, wall behind door, 3 locations” beats “paint”.
- 05Type
- Incomplete, Defective or Damaged. A punch list mixes all three, and they are read differently: incomplete work is a schedule number, defective work is a quality number, damage is a question of who did it.
- 06Trade
- The scope the item belongs to: painting, electrical, Division 10 specialties.
- 07Subcontractor
- The company responsible. Separate from Trade, because one sub can carry several scopes and one scope can be split between subs.
- 08Photo
- The filename of the photo taken at the punch walk. The photo is the item; the row is where it is filed.
- 09Punched by
- Whose walk found it: the GC’s pre-punch, the architect, the owner’s rep, commissioning. The same room gets walked three times, and the reader needs to know which list this came from.
- 10Date punched
- The date it was found on the walk. Not the date it was typed up.
- 11Close by
- Life safety, Substantial completion or Final completion. Life safety is today. Substantial completion items hold up the certificate; final completion items are the ones attached to it, closed before final payment.
- 12Due
- The fix-by date, set when the item is issued to the sub and visible to them.
- 13Status
- Open, Issued, Sub complete, Closed or Rejected. The sub moves an item as far as Sub complete. Rejected means the back-punch failed and the item goes back out.
- 14Sub completed on
- The date the sub said it was done, with their photo. Their claim, kept apart from the close-out.
- 15Back-punched by
- Who checked the fix against the original photo, on your side. Not the sub.
- 16Closed on
- The date back-punched and closed. On a sheet it is the only record of when the item changed, so fill it in.
- 17Notes
- Anything else: the dispute, the re-issue, the access arrangement. Never a substitute for the columns.
Four punch items from the second floor
P-0207, the scuffs. Damaged, not defective: the painter’s work was fine until the hardware went on. The Type column is what lets that conversation happen on the sheet rather than on site. Found on the GC’s pre-punch, so it is closed before the architect ever sees the room, which is what a pre-punch is for.
P-0208, the exit sign. Life safety, so it closes today, not by a milestone. Found, fixed and back-punched in one day by someone other than the super who found it. One row, every column filled.
P-0219, the grab bar. Incomplete: the blocking is in, the bar is not. Punched by the architect and it has to close before substantial completion, because nobody certifies a restroom without one. The sub says it is done, so it sits at Sub complete until someone on your side has checked it, and the note says what to check.
P-0231, the storefront door. The owner’s rep found it, and it can wait for final completion. The sub adjusted the sweep and said done; the back-punch found the gap still there at the bottom corner, so the status is Rejected and the note says why. This is the row the Back-punched by column exists for.
Where a punch list breaks
A punch list in a spreadsheet works for one walker, one floor and a week or two. It breaks in three predictable ways, and all three arrive between the first punch walk and final payment.
Questions about the punch list
Keep the columns. Give them one home.
Whatever holds this list should give you one copy for every walker, the photo attached to the item rather than named in it, the sub’s claim kept separate from the back-punch, and a Closed that only your side can set. If the sheet is doing that, keep it.
When it stops, defect management software covers what a system has to do with the same columns. In IssuesId the Type field keeps defects and incomplete works apart, items are issued to subs in bulk from a filtered list, and subs open their items from an email link with a proof photo, with only your side able to close. Large punch lists on data centre builds run the same way. The words are in the glossary under punch list and incomplete works; the same list in Canadian terms is the deficiency list template, and in British and Australian English the snag list template.