Punch list template

A construction punch list template, with the columns explained.

Seventeen columns, four worked punch items from one floor of a medical office fit-out, and one line on why each column is there. Who punched it, whether it is incomplete, defective or damaged, and whether it has to close before substantial or final completion, all on the sheet. Download it, copy it into a sheet, or read where a punch list breaks. No form, no email.

17 COLUMNS · 4 EXAMPLE PUNCH ITEMS · NO GATE
Item #FloorRoomDescriptionTypeTradeSubcontractorPhotoPunched byDate punchedClose byDueStatusSub completed onBack-punched byClosed onNotes
P-02072Exam 214Paint touch-up, wall behind door, scuffs from hardware install, 3 locationsDamagedPaintingBrightline PaintingIMG_3311.jpgGC pre-punch2026-10-06Substantial completion2026-10-10Closed2026-10-09K. Brooks (super)2026-10-09Hardware sub accepted the damage; painter back-charged per agreement.
P-02082Corridor 2AExit sign over door 2A-3 not illuminated on battery testDefectiveElectricalLakeside ElectricIMG_3314.jpgGC pre-punch2026-10-06Life safety2026-10-06Closed2026-10-06D. Ortiz (QA)2026-10-06Battery pack replaced same day; 90-minute test passed.
P-02192Restroom 2BGrab bar not installed at water closet, side wall; blocking in placeIncompleteSpecialtiesSummit SpecialtiesIMG_3342.jpgArchitect2026-10-08Substantial completion2026-10-13Sub complete2026-10-13——Check mounting height against the accessibility detail at back-punch.
P-02311Lobby 101Storefront door threshold, daylight visible at latch side, bottom cornerDefectiveGlazingClearview GlassIMG_3360.jpgOwner’s rep2026-10-09Final completion2026-10-23Rejected2026-10-20K. Brooks (super)—Back-punch 21 Oct: sweep adjusted, gap still at bottom corner. Re-issued.
Scroll sideways for the rest of the columns. The four rows are the worked examples further down; the file carries the same four so you can see the shape before you delete them.
The columns

What each column is for

A punch list does two jobs: it gets each item to the sub who owns it, and it proves each item was back-punched before it closed. The first twelve columns do the first job; the last five do the second, and they are the ones a walk sheet usually leaves out.

01Item #
A permanent number, assigned once and never reused. It does not encode the floor, the room or the sub, because all three can change and the number must not.
02Floor
Floor or level, as its own column so a filter for the second floor returns the second floor.
03Room
The room number or name from the drawings. “Exam 214” is a room; “the one by the nurse station” is not.
04Description
What is wrong or unfinished, where on the thing, and how much. “Paint touch-up, wall behind door, 3 locations” beats “paint”.
05Type
Incomplete, Defective or Damaged. A punch list mixes all three, and they are read differently: incomplete work is a schedule number, defective work is a quality number, damage is a question of who did it.
06Trade
The scope the item belongs to: painting, electrical, Division 10 specialties.
07Subcontractor
The company responsible. Separate from Trade, because one sub can carry several scopes and one scope can be split between subs.
08Photo
The filename of the photo taken at the punch walk. The photo is the item; the row is where it is filed.
09Punched by
Whose walk found it: the GC’s pre-punch, the architect, the owner’s rep, commissioning. The same room gets walked three times, and the reader needs to know which list this came from.
10Date punched
The date it was found on the walk. Not the date it was typed up.
11Close by
Life safety, Substantial completion or Final completion. Life safety is today. Substantial completion items hold up the certificate; final completion items are the ones attached to it, closed before final payment.
12Due
The fix-by date, set when the item is issued to the sub and visible to them.
13Status
Open, Issued, Sub complete, Closed or Rejected. The sub moves an item as far as Sub complete. Rejected means the back-punch failed and the item goes back out.
14Sub completed on
The date the sub said it was done, with their photo. Their claim, kept apart from the close-out.
15Back-punched by
Who checked the fix against the original photo, on your side. Not the sub.
16Closed on
The date back-punched and closed. On a sheet it is the only record of when the item changed, so fill it in.
17Notes
Anything else: the dispute, the re-issue, the access arrangement. Never a substitute for the columns.
Filling it in

Four punch items from the second floor

P-0207, the scuffs. Damaged, not defective: the painter’s work was fine until the hardware went on. The Type column is what lets that conversation happen on the sheet rather than on site. Found on the GC’s pre-punch, so it is closed before the architect ever sees the room, which is what a pre-punch is for.

P-0208, the exit sign. Life safety, so it closes today, not by a milestone. Found, fixed and back-punched in one day by someone other than the super who found it. One row, every column filled.

P-0219, the grab bar. Incomplete: the blocking is in, the bar is not. Punched by the architect and it has to close before substantial completion, because nobody certifies a restroom without one. The sub says it is done, so it sits at Sub complete until someone on your side has checked it, and the note says what to check.

P-0231, the storefront door. The owner’s rep found it, and it can wait for final completion. The sub adjusted the sweep and said done; the back-punch found the gap still there at the bottom corner, so the status is Rejected and the note says why. This is the row the Back-punched by column exists for.

The limit

Where a punch list breaks

A punch list in a spreadsheet works for one walker, one floor and a week or two. It breaks in three predictable ways, and all three arrive between the first punch walk and final payment.

Punch week
Three walks, three lists
The super pre-punches the second floor on Monday, the architect walks it on Wednesday, the owner’s rep on Friday. Three lists with three names for the same exam room, the scuffs on two of them and the restroom grab bar on one, because each walker assumed the others had it. A punch list with more than one copy is several punch lists.
The week before substantial completion
Sub complete becomes closed
Thirty items go to Closed from one email that said “2nd floor punch done”. Nobody back-punched. The architect walks Restroom 2B for the certificate and the grab bar is at the wrong height, on a list that says it was closed by the people who installed it.
Between substantial and final
The attached list goes stale
The items still open at substantial completion went out attached to the certificate. Six weeks later the owner asks which are done before releasing final payment, and the answer is in the super’s copy, the architect’s copy and a forwarded email, none of which agree.
Asked alongside the download

Questions about the punch list

What is a punch list in construction?
The list of work still to be completed or corrected before a project is accepted as complete and final payment is released. It is walked room by room near substantial completion, and each punch item is issued to the subcontractor responsible and back-punched before it closes. In the UK, Ireland and Australia the same list is a snag list.
What should a punch list template include?
Seventeen columns, in this template: a permanent item number, floor, room, the description with its extent, the type (incomplete, defective or damaged), trade, subcontractor, photo, whose walk found it, the date punched, whether it must close by substantial or final completion, the due date, status, the date the sub said it was done, who back-punched it, when it closed, and notes.
Who prepares the punch list, and when?
On AIA-form contracts, the contractor prepares the list of items to be completed or corrected when it believes the work is substantially complete, and the architect inspects and adds to it. The list is attached to the certificate of substantial completion with a period to finish it, and an item left off the list is still the contractor’s to complete. Most GCs pre-punch their own list before the architect walks.
What is a back-punch?
The re-inspection of a punch item after the sub says it is done: someone on the GC’s or owner’s side checks the fix against the original photo and either closes the item or rejects it back to the sub. Keeping the sub’s “complete” apart from the back-punch is what stops a list from closing itself.
Is the punch list template free, and in what format?
Yes. An Excel workbook with drop-downs for Type, Punched by, Close by and Status, the header row frozen and a second sheet explaining the columns, or a CSV with the same columns. Four worked punch items from a medical office fit-out are included. No form, no email.
What to do about it

Keep the columns. Give them one home.

Whatever holds this list should give you one copy for every walker, the photo attached to the item rather than named in it, the sub’s claim kept separate from the back-punch, and a Closed that only your side can set. If the sheet is doing that, keep it.

When it stops, defect management software covers what a system has to do with the same columns. In IssuesId the Type field keeps defects and incomplete works apart, items are issued to subs in bulk from a filtered list, and subs open their items from an email link with a proof photo, with only your side able to close. Large punch lists on data centre builds run the same way. The words are in the glossary under punch list and incomplete works; the same list in Canadian terms is the deficiency list template, and in British and Australian English the snag list template.