Picture a 66-apartment building in Box Hill with a building permit issued in August 2027. Somewhere around the end of 2030, fifteen to eighteen months after the occupancy permit, a building assessor will walk it. Every lot and the common property. They will write a report listing the reportable defective work, and it will go to the developer, the owners corporation, the builder and the Building and Plumbing Commission. The developer has to fix what is in it. Six months later the assessor comes back for the final inspection, and anything still open can be paid out of a bond worth 2% of the build cost.
That is the developer bond scheme, and it applies to residential apartment buildings of four storeys or more with a building permit issued from 1 July 2027. The regulations were made in June 2026. The regulatory impact statement put the typical bond at about $610,000 for a building that size, held for around three and a half years.
The assessor's report is a second opinion on your own list
Here is my view. If the assessor's preliminary report surprises the developer, the defects period has already been lost.
On a building that size the impact statement assumes about two defects per lot, so 132 across the building. A developer who has run the defects period properly already knows most of them. They came in from residents on QR cards in the first year, were typed, issued to the trades, fixed and checked. The assessor's report should read like an audit of that list: here are the 100 that were fixed, here are 25 still open that you knew about, here are 7 you missed. That is a manageable month.
A developer who ran the defects period on an inbox gets 132 items as news. Then they have six months to fix them with trades who left site two years ago, before the final inspection decides how much of the bond goes to the owners corporation.
What has to change in the defects period
Three things, none of them exotic.
The common property needs an owner on the developer's side. Residents report their own lots. Nobody reports the fire stair, the basement waterproofing, or the roof membrane over the plant deck until it leaks into somebody's lot. The assessor will walk all of it. Somebody on the developer's team should walk it first, at month nine and month twelve, and raise what they find as records against the common areas.
Defect and maintenance have to be separated as items arrive. The assessor reports defective work, not wear. A list where every resident complaint is filed as a defect is a list that overstates what the developer owes. Type each item as it lands, Warranty or Maintenance, with the reason, and the list is arguable on its own terms.
Fixed has to mean checked. The final report is about what is still defective, not what a trade said they did. Each closed item needs an after photo and the name of the person who looked at it. Otherwise the assessor finds a "closed" water stain that is back.
The handover pack is about to be regulated too
From 1 February 2027, new Class 2 buildings also need a building manual: permits, the common-property asset list, warranties, performance solutions, fire safety certificates, compliance reports. The surveyor checks it before the occupancy permit, and the owners corporation keeps it up to date every year. So the documents an assessor or a new committee will ask for in 2030 are becoming a required deliverable, not a courtesy.
I will be honest about where we fit and where we do not. IssuesId is not a building manual generator. It holds the defect and inspection register, the drawings it is pinned to, and the correspondence about each item. It does not compile permits and fire certificates into a manual. What it does is make the defects half of the story a report rather than a reconstruction. The Post PC Issues report lists what arrived after completion. The Issued To report shows what is still with each trade, oldest first, and the Internal Detailed report prints the full record, photos and all, for anyone who needs to check it.
Run it as if they are coming, because they are
For buildings permitted before July 2027 none of this is compulsory. But rectification orders already reach apartment developers, ten years back, and they are published. The bond scheme just puts a date and a dollar figure on what was already true. Somebody independent is going to read the defects list, and they are going to read the building.
Every date and its source is on Victoria's building reforms. The committee's side of the same building is the committee and the builder who stopped answering. This is general information, not legal advice; the regulations and the Commission's guidance apply.