Hold point
A hold point is a defined step in an inspection and test plan beyond which work must not proceed until a nominated party has inspected it and released the hold. A witness point is the weaker version: the party is notified and may attend, but work proceeds whether or not they do.
CONSTRUCTION DEFECT GLOSSARY·UPDATED OCTOBER 2026
Keeping this on a live job? IssuesId keeps every defect and inspection on one register, with the photo, the trade who owns it and who signed it off. Try it on one live project for two weeks, no card.
Where the word is used
Quality-management language used the same way worldwide, from ISO 9001 and from the inspection and test plans on infrastructure and industrial jobs. Common on any pour, any weld, anything that is about to be covered up.
On site
The classic hold point is the pre-pour check: reinforcement cover, chairs, formwork, before concrete hides all of it. A hold point waved through because the pump was booked is how a non-conformance becomes a demolition. The record has to show who released it and when.
Hold, witness, surveillance
One slab pour, three kinds of point
Hold point: reinforcement before the pour
Bar size, spacing, laps and cover, checked by the structural engineer. The pump does not start until the engineer has inspected and released it, because once the concrete is in nobody can look again.
Witness point: the slump test
The builder’s QA is notified before the trucks arrive and may come to watch the docket check and slump test. If they do not come, the pour goes ahead and the test record stands on its own.
Surveillance: placement and finish
Nobody is notified and nothing waits. The builder’s QA checks compaction, level and finish as the work proceeds, at their discretion, and records what they saw.
What the record has to show
For a hold point, who released it and when, before the next step started. For a witness point, that the notice was given and whether the party attended. A blank against a hold point means the work should not have proceeded.
On the record
How IssuesId holds it
A question on an IssuesId checklist can be marked as a hold point. The checklist page shows a marker while a hold point is outstanding, the organisation-wide list of checklists flags every open hold point across every project, and a subcontractor’s share link only reaches the questions between the last released hold point and the next one.
Asked alongside
Questions people ask
What is a hold point?
A step in the work that must not proceed until a nominated party, often the engineer or the client’s representative, has inspected and released it. It is written into the inspection and test plan, and the release is recorded with a name and a time.
What is the difference between a hold point and a witness point?
At a hold point work stops until the inspection happens. At a witness point the party is notified and may attend, but the work proceeds whether they come or not. Hold points are for what cannot be undone; witness points are for what can be checked later.
Can work continue past a witness point if nobody attends?
Yes, once the notice the inspection and test plan or the contract requires has been given. That is the difference from a hold point, where work waits for the release however long it takes. Record that the notice went out and when, because the record is what shows the step was offered for inspection.
What does H, W and S mean on an ITP?
H is a hold point: work stops until that party inspects and releases. W is a witness point: that party is notified and may attend. S is surveillance: that party monitors as the work proceeds, with no notice and no waiting. Each party on the plan gets its own code at each step, so one step can be an H for the engineer and a W for the builder.
Related terms
Definitions describe common usage and the usual shape of standard-form contracts. Your contract and your jurisdiction’s building law set the terms that apply to your job. The whole list is at the glossary.